New planning battle kicks off

7/10/09

It is now clear that the Harbour Revision Order that was enacted on September 16th gives Cornwall Council and the Route Partnership most of the permissions that they need to build their passenger and freight terminals on Battery Rocks beach. Importantly though they still need to secure Listed Building Consent before any work can commence.

The Harbour Revision Order (HRO) was applied for and the window for objections closed in 2005. At the time no-one knew about the HRO and what it meant for Penzance seafront and now we are being denied the opportunity to object to the totality of the plans through the normal planning process.

Indeed, when Cornwall Council applied for planning permission in May of this year they cannot have been aware of the planning implications of the HRO or they wouldn’t have made the applications they did. Now they know and when they resubmit their plans next week it will only be for a small part of the works that were contained in the previous planning applications.

However, Cornwall Council still need to secure “listed building consent” for the whole of the plans; the pier extension, rock armouring and the area they are creating for a passenger and freight terminal all impact on the listed South and Lighthouse Piers. Without this consent the project cannot go ahead. However, the final decision about whether or not to grant listed building consent cannot be taken locally; the application for listed building consent will go before the local planning committees and they can make a recommendation but the final decision will be taken by the Secretary of State who will be advised by English Heritage.

Cornwall Council will also have to apply for planning permission for certain elements of the scheme not covered by the HRO; these include construction of a covered walkway, the installation of new gates on the entrance to the reclaimed area, a temporary works access to the site, and the new seawall above reclaimed ground level (the wall up to ground level is included in the HRO). Obviously the project cannot go ahead without the new seawall!

Something called “prior approval” is also needed for certain other works, and this can be withheld by the planning authorities in certain circumstances. There is some uncertainty about what requires “prior approval”. The planning department’s legal advice says that only the pier extension requires prior approval but our own reading of the regulations suggests this may also extend to the rock armouring, reclaimed area and the passenger and freight terminals. This is important because the planning authority can withhold consent if the development could reasonably be carried out on land and/or the design/appearance could be improved. The FoPzH will be seeking its own expert advice to clarify exactly what the “prior approval” applies to. However Cornwall Council has already advertised their intention to apply for “prior approval” for the pier extension and the public have until October 21st to make representations to the Council.

The FoPzH are also trying to find out if the planning department are correct in saying that Conservation Area consent is not required. It is likely to be just one interpretation of the regulations, and an odd one given the scale of the development and its proximity to the Conservation Area.

The FoPzH are also continuing to investigate options for challenging the HRO.

The Cornwall Council briefing describing their interpretation of the planning situation in respect of the scheme can be found below. This was presented to members of the West Area and Strategic planning committee at a meeting in Penzance on October 5th.

Cornwall Council planning briefing : download pdf | view pdf

Other Stories

20/8/10
Andrew George condemns Option A and the "bullying and intimidation" of its supporters

19/8/10
Secretary of State declines to call in LBC application

11/8/10
Joint appeal for DfT investigation of Route Partnership project

6/8/10
Planning committee chair describes Penzance Harbour process as “absolute shambles”

16/7/10
European Parliament to investigate Pz Harbour scheme

12/7/10
URGENT: Please write to Norman Baker MP

28/6/10
South Pier historic listing elevated to Grade II *

23/6/10
Cllr Hicks guilty of “unreasonable and excessive personal attack”

14/6/10
Golden opportunity to reassess Scilly Link scheme

9/5/10
Tender outcome predictable

4/5/10
Vote to save historic seafront

24/3/10
Object to Option A environment consents

20/3/10
Help us secure a Public Inquiry

17/3/10
Option PZ planning application submitted

9/3/10
Misinformation, threats and false promises win the day

9/3/10
Objectors win letters battle hands down

8/3/10
Planning Committee volt face

7/3/10
Option A support so much “smoke & mirrors”

4/3/10
Public give Option PZ a warm welcome

3/3/10
CPRE object to LBC application for Option A

1/3/10
Town Council rejects Option A again

25/2/10
“Option PZ” should unite community

5/3/10
Planners meet this coming Monday

24/2/10
Put Penzance First

24/2/10
Option A Myths

22/2/10
Council harbour decision making "grossly defective"

8/2/10
Council resubmit application for Listed Building Consent

28/1/10
A sad day for Cornwall Council

25/1/10
English Heritage objection to Option A “still stands”

22/1/10
MP convenes meeting to discuss alternatives to Option A

13/1/10
Business community calls for end to Option A plans - now 30 sign-ons

1/1/10
Campaign continues in 2010

14/12/09
Planning Committee REFUSES application - 669 write to object

10/12/09
Packed meeting sends clear message to planning committee

2/12/09
English Heritage say NO to building on Battery Rocks beach

30/11/09
Planning Committee to meet in Penzance on December 10th & 14th

23/11/09
“RMV White Elephant” or, why two ships are better than one

19/11/09
Deadline for objections extended

16/11/09
Out of control Council circumvents normal planning procedures, makes mockery of local democracy

14/11/09
Friends ask Secretary of State to “call in” harbour proposals

13/11/09
Packed house hears extraordinary history of pier

12/11/09
Tinner Challenges Planners

2/11/09
Complaint of maladministration leading to injustice

28/10/09
New Option A planning applications submitted - YOU MUST OBJECT AGAIN!

22/10/09
Option A: two years of hell!

16/10/09
Isles Council continues its bully-boy tactics

9/10/09
Packed public meeting rejects plan to build on Battery Rocks beach

7/10/09
New planning battle kicks off

1/10/09
Offensive remarks a sign of poor judgement

30/9/09
Public Meeting: St John’s Hall, October 9th at 7:30pm

29/9/09
Friends launch Fighting Fund to defend historic seafront

28/9/09
Cornwall Cabinet decision based on biased and misleading information

13/9/09
Cabinet to consider resubmission of Battery Rocks planning application

11/9/09
One ship option is NOT cheaper to operate

25/8/09
Alternative options report fudges figures to support original scheme

25/8/09
MP says Route Partnership scheme "politically undeliverable"

24/8/09
Route Partnership plan will harm regeneration in Penzance

20/8/09
Public rejects Route Partnership scheme (AGAIN)

12/8/09
A reminder of what we stand for...

30/7/09
Scilly Link unviable from Falmouth

27/7/09
Route Partnership attempt to undermine local democracy - historic seafront still in danger!

7/7/09
Route Partnership continue to promote development on Battery Rocks beach

6/7/09
Meadery site "may" be best option for passenger terminal

5/7/09
Friends comment on draft Alternative Options Appraisal

3/7/09
Breakdown of objections published

12/6/09
Planning application withdrawn

19/5/09
Cornwall Council move to consider alternatives

4/5/09
Route Partnership talk about alternatives

1/5/09
Jubilee Pool association joins fight against harbour development

22/4/09
Planners overwhelmed by objections to Route Partnership plan

22/4/09
Planning permission sought for works depot

15/4/09
Time to talk about alternatives

9/4/09
Planning application to be considered on July 7th

26/3/09
Objections still accepted

16/3/09
Object now to stop Battery Rocks beach development

10/3/09
English Heritage unhappy with Route Partnership scheme

5/3/09
Harbour development planning notices published today

4/3/09
Route Partnership admits to exhibition photomontage error

3/3/09
Route Partnership refuses to meet protesters

2/3/09
Traffic survey reveals advantages of out-of-town freight depot

25/2/09
Route Partnership defy public and submit Battery Rocks planning application

23/2/09
Department of Transport request review of Route Partnership plans

19/2/09
Friends of Penzance Harbour call on Councils to provide political leadership

16/2/09
Call for Scillonians to look again at Route Partnership plans for the Islands

11/2/09
Town Council says "no" to Route Partnership scheme

10/2/09
Elected representatives must reject Route Partnership plan for Penzance

5/2/09
Department of Transport admit there is NO time limit on funding

26/1/09
Friends of Penzance Harbour make formal complaint about exhibition

23/1/09
Massive opposition to plans for Penzance harbour